SANTOS has brought gas into its LNG production Train 1 at the GLNG project on Curtis Island at Gladstone.

The delivery of gas is a key milestone in the ongoing plant testing and commissioning process, and keeps GLNG on track for first LNG around the end of the third quarter.

Over the coming weeks, the GLNG team will start up Train 1's front end pre-treatment units before chilling down the cold end refrigeration units to make LNG.

Santos managing director and chief executive officer David Knox said GLNG was on track to produce first LNG around the end of the quarter.

"GLNG is progressing extremely well. Our upstream facilities are fully operational and we are in the final stages of commissioning on Curtis Island," Mr Knox said.

"As we continue to hit our key milestones, we know exactly what remains to be done and we're focused on safely delivering GLNG on time and on budget."



150-year first for Gladstone church

150-year first for Gladstone church

A new sign of the times at Gladstone Presbyterian Church.

Controversial 1770 development decision spurs robust debate

premium_icon Controversial 1770 development decision spurs robust debate

Councillors vote to approve 1770 development despite reservations.

PROPERTY LIST: Peek inside these open homes this weekend

PROPERTY LIST: Peek inside these open homes this weekend

From Tannum Sands to Calliope there is something for everyone.

Local Partners