MORE than a month into exporting gas, the QCLNG berth at Curtis Island has handled four ships.

The fourth fully loaded vessel departed last week and the fifth is due to arrive at the weekend.

That number is consistent with QGC's planned schedule for the commissioning phase of the first production train.

When the plant is at full production capacity next year, up to 120 vessels per year on average will visit QCLNG.

Bechtel will continue working on QCLNG throughout 2015 to finalise commissioning and production testing of the LNG processing Train 1, and to finalise construction and then commission Train 2 in the second half of the year.

A company spokesman said the LNG companies with housing facilities used for fly-in fly-out workers on Curtis Island were working with government authorities to assess a number of options to house contract workers that would be required for maintenance from time-to-time.



Shipping company fined for dumping on Great Barrier Reef

Premium Content Shipping company fined for dumping on Great Barrier Reef

The Iron Gate was bound for Gladstone when the chief officer authorised dumping of...

Gladstone man taunted partner after brutal assault

Premium Content Gladstone man taunted partner after brutal assault

The man’s sickening actions had severe consequences.

Gladstone man broke ex-girlfriend’s nose

Premium Content Gladstone man broke ex-girlfriend’s nose

The attack happened at a West Gladstone residence.