News

GPC ignored bund wall advice, documents say

THE Gladstone Ports Corporation ignored its approved plans and external advice when it failed to build a rock covering over the geotextile fabric which tore on a bund wall in Gladstone harbour, confidential government documents have revealed.

An independent engineer who examined the failure of the Fisherman's Landing bund wall for the Federal Government's review has revealed the failure to build a rock covering was the key problem that led to sediment leaking through and under the bund in 2011 and 2012.

The failures on the wall were one of the key problems on the controversial Western basin dredging project and associated works, which coincided with a fish disease outbreak in the harbour.

And while the review panel members, led by CSIRO scientist Dr Andrew Johnson, had other expertise, no specific engineering expertise was originally proposed in the review's terms of reference.

It was not until Engineers Australia publicly complained about the lack of such expertise on the panel that it sought coastal engineer Dr Peter Cummings' independent advice.

Dr Cummings' confidential report to the panel has revealed that in the final construction of the bund wall, the port ignored its own EIS designs and advice from consultants to complete the rock covering over the geotextile fabric to prevent it failing.

His report, obtained under Freedom of Information laws, shows that while the consultant's advice was "recognized good industry advice"; "the as-built wall does not appear to have followed (it)".

"The design as built did not meet industry best practice and/or recognized industry standards," his report reads.

While the port's inquiry submission said it received other advice from contractors that laying the geotextile on the surface would have the "same filtration effect" as laying it under the original rock covering proposed, Dr Cummings said such advice was a "departure from normal practice".

"The use of an unrestrained exposed geotextile filter on the internal wall of the bund is not accepted practice because the geotextile is susceptible to disruption by hydraulic pressure and wave action," his report states.

Aerial view of Fisherman's Landing and the Bund Wall in 2013.
Aerial view of Fisherman's Landing and the Bund Wall in 2013. Brenda Strong

Dr Cummings said that while the approved plans and external advice originally stipulated the use of the rock covering; "something happened at the very end and I don't know what it is and the review panel didn't know what it was".

"If you like it was at the nuts and bolts level that something happened and the rock covering for the geotextile was not applied," Dr Cummings said.

The actual geotextile fabric used on the bund wall has also been questioned by engineers who worked on the project, who have argued the fabric used was not sufficient to prevent damage and leaks.

But Dr Cummings said he believed that irrespective of what specific geotextile was used in the project, the failure to cover and weigh down the fabric properly was the "key problem".

But despite the failures in building the bund wall, Dr Cummings said the remediation works taken almost 12 months after the bund wall was confirmed to be leaking was "industry best practice".

Dr Cummings also said that during his inquiries, the Department of Environment refused to allow him to meet with the port to examine the issues in more detail, rather than relying on the port's submission to the inquiry and regulatory documents.

"It would've been preferable if I could have spoken to them, I probably would've found out a bit more," he said.

"I was really examining documents provided to me by the department and I had one or two other documents I obtained myself.

"The people actually on the inquiry did interview them but because I wasn't an official panel member, they said no."

The Federal Environment Department did not respond to questions regarding Dr Cummings' original report or the failure to allow him to meet with the port directly during the review.

A spokeswoman for Gladstone Ports Corporation refused to answer questions.

Topics:  bund wall, environment, federal government, gladstone harbour, gladstone ports corporation




Owner told he has no insurance as Gladstone home burns

The owner of this New Auckland home had been renovating it for three years this October and yesterday it went up in flames.

Three years of renos go up in smoke

UPDATE: Migaloo ventured past Gladstone today

FILE: Migaloo is expected to cruise past Gladstone this weekend.

All-white humpback whale Migaloo returns

UPDATE: Chemical spill closes road as police investigate death in Gladstone horror crash

A driver had died in a crash on Hanson Rd.

POLICE investigate the death of a 23-yearold in yesterday's crash.

Latest deals and offers

#SaveMarinaJoyce: How ISIS theory took over youtube channel

One young Youtuber accidentally gave rise to a conspiracy theory

Talking whiskey with Jack Daniel’s master distiller

It all comes down to the distillery

SIXTY MILES AHEAD sign with Eclipse Records, prepare new album 'Insanity'

Sixty Miles Ahead sign with Eclipse. Photo Contributed

Sixty Miles Ahead to release new album on Eclipse

Thy Art Is Murder are killing it

See Thy Art is Murder on their killer tour happening right now. Photo Contributed

We talk with Thy Art is Murder about touring, babies, and new music

Date announced for Prince tribute concert

A Prince tribute concert will take place later this year

Matt Damon is taking a break from acting

Matt Damon is taking a break to spend time with his family

Queensland's $1 town goes under the hammer today

The township of Yelarbon is up for sale.

Unprecedented auction of town's business centre with no reserve

Work starts on $15M Caloundra apartment building

Turning the first sod at the Aqua View Apartments site in Kings Beach are (from left) husband-and-wife developers Alex Yuan and Stella Sun with construction company Tomkins director Mike Tomkins and Councillor Tim Dwyer.

Developers excited about addition to Kings Beach skyline

72-year-old Coast developer set to start new project

GREEN LIGHT: The Cosmopolitan has been approved for development at Cotton Tree.

Meet the Canberran set to deliver another chapter for Coast suburb

Plans revealed for 1500-lot 'master-planned community'

Precinct will be bounded by Boundary St and Shoesmith Rd

Ecco Ripley sales run sparks prime release

MOVING IN: Sekisui House has announced the release of more residential blocks at Ecco Ripley.

Sekisui House is preparing to unveil more land at Ecco Ripley

The climb is slow but property on the way up

Michael Matusik, director of Matusik Property Insights.Photo Allan Reinikka / The Morning Bulletin

The improvement would be mild when compared to past cycles